Deh Gah School Boiler Replacement
Contract ID: SC415929
Status
This contract was awarded by Public Works & Services to Taylor & Company.
The contract is complete.
There were 2 change orders.
Dates
- Start Date
- Jun 29, 2009
- Current End Date
- Jul 31, 2009
- Potential End Date
- Unknown
Description
Provide installation services, necessary equipment and parts for the replacement of the existing boilers/burners in the Deh Gah School.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Taylor & Company
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Hay River
- Original Value:
- $63,250.00
- Change Orders:
- $3,613.00 (2 changes)
- Current Value:
- $66,863.00
- Community:
- Fort Providence (Dehcho)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2009-10 | 1. cc417479 | $2,265.00 |
2009-10 | 2. cc418223 | $1,348.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.