Culvert Replacement
Contract ID: CT101192
Status
This contract was awarded by Transportation to Rowe's Construction Ltd..
The contract is complete.
There was 1 change order.
Dates
- Start Date
- Jun 05, 2012
- Current End Date
- Aug 31, 2013
- Potential End Date
- Unknown
Description
Remove and replace existing culvert with new culverts and all associated earthworks
Details
- Fiscal Year:
- Buyer:
- Transportation
- Contract Dates:
- to
- Supplier:
- Rowe's Construction Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Hay River
- Original Value:
- $298,460.00
- Change Orders:
- -- (1 change)
- Current Value:
- $298,460.00
- Community:
- Fort Smith (South Slave)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Road Construction Services
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2012-13 | 1. CC435040 | (unknown)* |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.
Help us improve OpenNWT