Embankment, Drainage Improvements and Asphaltic Surface Treatment

Contract ID: CT101333
Status

This contract was awarded by Transportation to Rowe's Construction Ltd..

The contract is complete.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 16, 2013
Current End Date
Sep 10, 2014
Potential End Date
Unknown

Description

Aggregate production, Embankment, sub-base and base course construction; Culvert replacement and ditch excavation; Road way preparation and Asphaltic surface treatment.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Rowe's Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Simpson

Original Value:
$3,270,244.75
Change Orders:
$114,568.25 (2 changes)
Current Value:
$3,384,813.00

Community:
<Various Communities>
Process:
Negotiated
Method:
Direct
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2013-14 1. CC439034 $200,016.00
2014-15 2. CC445015 -$85,447.75

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2013-14 April 1, 2013 March 31, 2014 Report
2013-14 Aug. 16, 2013 Aug. 31, 2014 Report