Engineering Services

Contract ID: SC570247
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by NWT Housing Corporation to Maskwa Engineering Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jun 17, 2009
Current End Date
Jul 20, 2009
Potential End Date
Unknown

Description

Location of lot corners, building footprints, and driveway locations for 10 lots in Fort Liard, NT.

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
Maskwa Engineering Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Hay River

Original Value:
$8,940.00
Change Orders:
--
Current Value:
$8,940.00

Community:
Fort Liard (Dehcho)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 June 17, 2009 July 20, 2009 Report