Design/Build - Wood Pellet Boiler Systems
Contract ID: SC520996
Status
This contract was awarded by NWT Housing Corporation to Taylor & Company.
The contract is complete.
There were 4 change orders.
Dates
- Start Date
- Feb 07, 2014
- Current End Date
- Jun 30, 2015
- Potential End Date
- Unknown
Description
Design/Build - Wood Pellet Boiler System & Oil-Fired Backup Boiler System Proposal Documents will be available on the NWT Construction Association's Website at www.nwtca.ca
Details
- Fiscal Year:
- Buyer:
- NWT Housing Corporation
- Contract Dates:
- to
- Supplier:
- Taylor & Company
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Hay River
- Original Value:
- $263,739.00
- Change Orders:
- $24,347.00 (4 changes)
- Current Value:
- $288,086.00
- Community:
- Fort Resolution (South Slave)
- Process:
- Request for Proposal
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2014-15 | 1. CA103549 | $1,424.70 |
2015-16 | 2. CA103555 | $1,500.00 |
2014-15 | 3. CA5752 | $21,422.30 |
2015-16 | 4. CA5753 | (unknown)* |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.