Fort Simpson Bunkhouse Handicap ramp

Contract ID: SC422454
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to Rowe's Construction Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Sep 11, 2008
Current End Date
Sep 11, 2008
Potential End Date
Unknown

Description

Repair Handicap Ramp

Details

Fiscal Year:
Buyer:
Public Works & Services
Reported Contract Buyer:

Contract Dates:
to

Supplier:
Rowe's Construction Ltd.
Supplier BIP Status:
--
Supplier Location:
Hay River, NT

Original Value:
$5,330.00
Change Orders:
--
Final Value:
$5,330.00

Community:
--
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
--

Contract Added:
Feb. 1, 2024
Source:
CRRS Extract

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2008-09 Sept. 11, 2008 Sept. 11, 2008 Report